Feasibility of crystal shadowing for SX at 8 GeV

13.02.2024, 14:20
20m
TFZ Wiener Neustadt

TFZ Wiener Neustadt

Viktor Kaplan-Straße 2, 2700 Wiener Neustadt, Austria
Oral presentation Managing Extraction Efficiency

Sprecher

Vladimir Nagaslaev (FNAL)

Beschreibung

Mu2e experiment, searching for a super rare mode of the CLFV decay of muon into an electron is in preparation for data taking at Fermilab’s Muon Campus facility. The experiment requires the 8 GeV proton beam continuous delivery aided by the Slow Extraction (SX) from the Delivery Ring. The first beam commissioning of the SX has been scheduled for FY2024. However, there was a possibility to start commissioning earlier, in FY2023. Here we will discuss our first experience and challenges with running SX in the Delivery Ring.