Visit to FAIR construction site

Europe/Berlin
Description
Pictures taken by Juergen Eschke in the occasion of a Site Visit of the APPA collaboration.
    • 15:00 15:01
      Transfer Building 1m
      pictures
    • 15:01 15:02
      Rebar steel 1m
      For various reasons we have an unusually high fraction of reinforcing steel. More than 60000 t will be used during shell construction, and each site visit is a good opportunity for impressive closeups.
      close-up, 10cm mesh width
      status before floor is cast
    • 15:02 15:03
      CBM Cave 1m
      The main part of the CBM cave is fully excavated and the ground is prepared for the floor slab.
      heads of foundation pillars
      View of CBM cave area